Scope of Work
- Spray Applied Ceiling Texture: 17,000 square feet
- Floor Tile Mastic: 135 square feet
- Thermal Mud Joint Fittings: 10 each
- Thermal Pipe Insulation: 45 linear feet
- Fire Doors: 15 each
- HVAC Duct Insulation: 5,000 square feet
Project Details
Gerken Environmental was retained by The University of Arkansas for the proper removal and disposal of asbestos materials in preparation of a renovation project within the Sigma Alpha Epsilon fraternity house. Gerken Environmental was required to work closely with East Harding Construction Company who was hired as the construction manager for the project. Gerken Environmental was awarded the project and was able to complete the project prior to student returning for fall classes on the campus.